118 Street (92 Avenue to 96 Avenue)

overview-114-street

Updates

The 118 Street Neighbourhood Road Improvements Project is substantially complete. Thank you for your patience as we worked together to improve 118 Street.

Overview

The 118 Street (92 Avenue to 96 Avenue) Roadway and Utility Improvements project is part of Delta's Neighbourhood Road Improvements Plan, which was introduced in 2012 to address aging roads and sidewalks in our community.

Proposed improvements along 118 Street includes:

  • Roadway widening along 118 Street to Delta’s local road standard (9.0m wide road width);
  • Roadway rehabilitation;
  • New sidewalk along the west side of 118 Street;
  • New roll over curb and gutter;
  • New boulevard trees;
  • Ditch infill and storm main upgrades as necessary; and,
  • New LED street lighting.

For more information, please review the preliminary plan and photo renderings (below).

Learn about the typical stages of construction for this project: Road Construction Process.

For more information, please review the preliminary plan and photo renderings below:

Before and After – Facing South




 


Before and After – Facing South




 

 


Before and After – Facing North




 

 

Project Timeline

Construction for the 118 Street project began Spring 2017 and is scheduled to be completed mid-July 2017.

Public Consultation

A Public Information Meeting was held November 16, 2016 to discuss the proposed design and construction timeline.

Reports and Related Documents

Contact Information

For more information, please email the Engineering Department or call 604-946-3260.
  • Upcoming Events

    Public Hearing
    September 19, 2017
    Board of Variance Meeting
    September 20, 2017

    All Events

  • Your Government

    Check out rewarding employment opportunities with Delta. 

    Learn More

  • Subscribe to our Newsletter

    Click Here
  • Find a Program/Activity