53 Street/Arthur Drive and 28 Avenue Roadway and Utility Improvements

Overview

The 53 Street/Arthur Drive and 28 Avenue Roadway and Utility Improvements project is part of Delta's Neighbourhood Road Improvements Plan, which was introduced in 2012 to address aging roads and sidewalks in our community. 

The proposed roadway and utility improvements along 53 Street/Arthur Drive and 28 Avenue include:

  • A new traffic signal on 53 Street/Arthur Drive at 28 Avenue including LED street lighting;
  • Roadway widening (on the west side of 53 Street/Arthur Drive) to provide dedicated southbound right and left turn lanes;
  • New dedicated westbound right turn lane on 28 Avenue;
  • Ditch infill along the west side of 53 Street/Arthur Drive including new storm sewer installation;
  • New drainage swale with lawnbasins along the west side of 53 Street/Arthur Drive for drainage;
  • New dedicated separated cycle lanes;
  • Bus stop improvements;
  • Delta watermain replacement; and,
  • Roadway rehabilitation.

A preliminary plan of proposed improvements is attached for information.

Update: New dedicated separated cycle lanes will also be included along 53 Street/Arthur Drive from the overpass over Deltaport Way to 34B Avenue as part of this project.

Learn about the typical stages of construction for this project:
Road Construction Process.

Project Timeline

Construction of this project is tentatively scheduled as follows:

  • Spring 2019 – Delta Watermain Construction
  • Summer 2019 – Roadwork Construction

Residents will receive another letter to notify them of the construction start date.

Photo Renderings

South-Facing




West-Facing



 


Public Consultation

A public consultation meeting was held on February 21, 2018.

Due to heavy snow and traffic issues during the Public Information Meeting on February 21, 2018, an additional Public Information Meeting was held on April 17, 2018.

Metro Vancouver Watermain Replacement

Metro Vancouver is planning to replace the watermain along 53 Street/Arthur Drive between 28 Avenue and 34B Avenue and along 28 Avenue between 52 Street and 53 Street/Arthur Drive.  This project will improve reliability of the water supply to the Tsawwassen area, including Tsawwassen First Nation (TFN) lands, and increase capacity to satisfy future demands.

Update: Metro Vancouver will be beginning watermain construction along 28 Avenue between 52 Street and 53 Street in October 2018.

For further information regarding Metro Vancouver’s project, please refer to their website: http://www.metrovancouver.org/services/water/construction-maintenance/construction-projects/south-delta-water-main-no-1-replacement

Contact Information

For more information, please email Engineering Department or call 604-946-3260.

  • Upcoming Events

    Roaming Rascals Halloween
    October 25, 2018

    All Events

  • Your Government

    Check out rewarding employment opportunities with Delta. 

    Learn More

  • Subscribe to our Newsletter

    Click Here
  • Find a Program/Activity